Wet facade: materials list and order of work

One list, so that you do not drive to the warehouse five times. The norms are for 100 m² of wall; multiply for your own area.

List for 100 m²

Order of layers

Clean and prime the wall. Fix the starter profile at the bottom, and on it the first row of slabs on adhesive, with joints staggered like brickwork. A day later, drive the dowels: one in the centre of each slab, the rest in the joints. Close corners and reveals with a corner bead with mesh. Apply a base layer of 3–4 mm, embed the mesh in it with a 100 mm overlap and cover it with a second layer, 5–6 mm in total. After 3–5 days, apply primer and decorative render, and a day or two later paint in two coats.

What is most often forgotten

The starter profile and the drip edge above windows — without them water gets under the insulation. A reserve of mesh for the overlap. Dowels of two lengths, if the house has both brick and concrete belts. And timing: the base layer must not be dried in July sun, so the facade is shaded or worked on from early morning.

Ordering in one list

The insulation, dowels, washers, mesh and corner beads from the list are in different sections of the shop, and the insulation, dowel and mesh calculators work them out for your area; adhesive, decorative render and paint are not in our range. The manager checks stock at the warehouse and puts the order together for a single delivery.